Key projects delayed due to site clearance obstacles

ĐBP - Currently, many key projects are being implemented in Điện Biên province, playing an important role in developing infrastructure and promoting economic growth.

In recent times, the provincial Party Committee and provincial People’s Committee have focused on decisive leadership, promptly resolving difficulties to accelerate the progress of these projects. However, to date, most projects have still not met their set schedules; the main reason is due to obstacles in site clearance.

Điện Biên province is implementing 6 key projects using state budget capital. Currently, most of these projects are behind schedule due to many obstacles in site clearance work.

The transport route project connecting key economic areas along the economic corridor of National Highways 279 and 12 is currently behind schedule, with construction volume only reaching nearly 72%. Photo: Văn Tâm

The compensation and site clearance for these projects must be carried out during the transition between the 2013 Land Law and the 2024 Land Law. Since July 1, 2025, with the implementation of the two-level local government model, commune-level People’s Committees have taken over all compensation, support, and resettlement tasks from the former district-level People’s Committees, while also implementing new decentralization and delegation of power in the land sector. Many tasks previously under the authority of the provincial People’s Committee are now assigned to commune-level People’s Committees, especially deciding on measures and other support levels according to Article 108 of the 2024 Land Law. In addition, some newly assigned officials have not yet firmly grasped the procedures and professional skills, causing site clearance work to be interrupted, lack synchronization, and affect the overall progress of the projects.

The work of compensation, support, and resettlement is vast, with complex procedures involving many steps, agencies, organizations, and people. Meanwhile, the local official workforce is insufficient, and their professional capacity is uneven, leading to slow processing of paperwork.

Determining land origin and ownership responsibility faces many difficulties due to the history of land management and use over many periods. Many households have not completed the legal procedures for registration, donation, transfer, or change of land use purpose as required, which prolongs the process of determining rights and compensation levels. Furthermore, inventorying assets on the land, cross-checking declarations, and determining the extent of damage for each household also takes a lot of time and gives rise to complaints and petitions, leading to delays.

The transport route project connecting key economic areas along the economic corridor of National Highways 279 and 12 must be completed in 2025. However, the project has not yet met its planned progress.

According to information from the provincial Management Board for Transport Construction Projects, the total value of completed construction and installation packages is estimated at nearly 72%, and cumulative capital disbursement has reached 84.48% of the assigned plan. The reason is the slow site clearance work, leaving contractors without “clean” ground to proceed with construction.

To date, the project has received 79.18 out of 83.28 hectares of ground, achieving 95.07%. Of this, Sam Mứn commune has completed 100% of its site clearance. The remaining localities include: Mường Thanh ward, which has handed over 88%; Điện Biên Phủ ward, 99%; Thanh Yên commune, 99.78%; and Thanh Nưa commune, 99.27%.

Đặng Đình Đắc, Deputy Director of the provincial Management Board for Transport Construction Projects, stated: “Basically, 4 packages have been completed. However, for packages 4, 5, and 6 related to the Mường Thanh ward area, site clearance is still an issue. In the coming time, the Board will continue to coordinate closely with local authorities to decisively implement compensation and support work to get clean ground, ensuring construction progress and project disbursement.”

The Project Management and Land Fund Development Board for Area 2 is the unit responsible for creating the site clearance compensation plan for the project’s scope in the communes of the former Điện Biên district. To date, it has issued land recovery decisions and approved 173 compensation, support, and resettlement plans, with a total recovered area of 382,467.1m² out of 382,660.9m², achieving 99.95% of the total area to be recovered from 1,283 households. The Board is currently continuing to submit and approve site clearance compensation plans to soon hand over clean ground to the investor. However, there are still some areas without a compensation plan, and some households have not agreed to receive money and hand over the land.

Such is the case of the household of Phạm Công Hưng in the former Thanh Hưng commune (now Thanh Nưa commune), whose compensation plan has not been approved due to claims that he had already received money during the implementation of the previous Hồng Khếnh reservoir drainage canal project. On August 29, 2025, the Thanh Nưa commune People’s Committee and relevant units investigated; Hưng affirmed he had not received compensation. However, some residents stated that Hưng’s father, Phạm Văn Tuyên, had received compensation for that project. The Thanh Nưa commune People’s Committee is currently continuing to verify and clarify the matter.

The contractor is focused on accelerating the construction progress of the Nậm Rốm River Basin Multi-Disaster Management Project in locations where the ground is clear.

The Nậm Rốm River Basin Multi-Disaster Management Project, with a total investment of over VND 981 billion, is also behind schedule due to site clearance obstacles. To date, the project has only received 77.5% of the clean ground.

This project has two main problems regarding support policies: one for households with land-lease contracts with the Điện Biên Agricultural Products Processing Joint Stock Company, and one for support for alluvial land along the river. Currently, the provincial People’s Committee has a special support mechanism for households with land-lease contracts with the company. However, the mechanism does not support households who have lease contracts but are still directly farming the land. As a result, when the compensation plan was approved, these households did not agree to receive the money and would not hand over the land.

For alluvial land along the river, plots used before July 1, 2014, are supported with 40% of the value of the same type of agricultural land. Plots used after this date receive no support, so many households disagree with the compensation plan.

Nguyễn Hữu Hiệp, Director of the provincial Management Board for Agricultural and Rural Development Projects, said: “In the coming time, the Board will coordinate with local authorities to focus on resolving difficulties in site clearance. At the same time, the Board also requires contractors to work in 3 shifts, 4 teams, to ensure progress and the disbursement of investment capital.”

Site clearance is the biggest “bottleneck” in implementing key projects in the province. To fix this, close and synchronous coordination between all levels and sectors and the consensus of the people are needed. In the context of changing the government model and applying the new Land Law, the province needs to strengthen training and professional guidance for commune-level officials, especially those directly involved in compensation and site clearance. It is necessary to enhance the proactivity of grassroots authorities and promote the role of leaders in communicating and mobilizing people to comply with compensation and support policies. Local authorities and relevant agencies must promote dialogue, publicize information transparently, and ensure all compensation plans are clearly understood and agreed upon by the people. For remaining complicated cases, records must be reviewed and re-verified to avoid prolonged disputes.

Site clearance is the first step, but it is also the decisive factor for the progress of every project. When this “bottleneck” is removed, key projects will have the conditions to accelerate, creating new momentum for the province’s socio-economic development in the time to come.

Phạm Trung
Comment

You have 500/500 characters left

Please enter 5 or more characters!!!

Recent news

  • 'Crop restructuring drives sustainable agriculture in Điện Biên

    Crop restructuring drives sustainable agriculture in Điện Biên

    ECONOMY -
    ĐBP - Điện Biên province is restructuring its crop mix, identifying the expansion of coffee, macadamia and fruit trees as the backbone of a green, sustainable agricultural development strategy. This orientation is set out in the provincial Party Executive Committee’s Resolution on restructuring the agricultural sector toward concentrated, green, smart and sustainable commodity production for the 2026-2030 period, with a vision to 2035.
  • 'Expanding market for local agricultural products

    Expanding market for local agricultural products

    ECONOMY -
    ĐBP - In Điện Biên province, in the context of agriculture shifting strongly from the mindset of “producing what we have” to “producing what the market needs,” bringing local agricultural products to become specialties and conquering larger markets is opening up a sustainable direction for farmers.
  • 'Unity dance by Đà River

    Unity dance by Đà River

    CULTURE - SPORTS -
    ĐBP - In the early days of 2026, when the morning mist still lingered on the water surface of the Sơn La Hydropower Reservoir, we were present in Mường Lay ward, Điện Biên province.
  • 'Well preparing for “Compassionate Tết” program

    Well preparing for “Compassionate Tết” program

    SOCIAL AFFAIRS -
    ĐBP - The “Compassionate Tết” program for the 2026 Lunar New Year (Tết) – the Year of the Horse is a humanitarian activity of deep significance, aiming to care for and support poor households and individuals in difficult circumstances in Điện Biên province, helping them have the conditions to enjoy spring and welcome Tết.
  • 'Điện Biên builds concentrated raw material areas

    Điện Biên builds concentrated raw material areas

    ECONOMY -
    ĐBP - In highland communes of Điện Biên province, agricultural production was previously mainly small-scale and fragmented by household. This led to difficulties in scaling up and organizing consumption according to the value chain.
  • 'Bringing digital government closer to people in Điện Biên

    Bringing digital government closer to people in Điện Biên

    SOCIAL AFFAIRS -
    ĐBP - From installing the VNeID app to completing administrative procedures on smartphones, the “Digital literacy for all” movement is steadily bringing digital government closer to the people of Điện Biên. Beyond making public services more accessible, the initiative is playing a key role in accelerating administrative reform and building a modern, efficient grassroots administration.
  • 'How Điện Biên needy people escape poverty

    How Điện Biên needy people escape poverty

    ECONOMY -
    ĐBP - Once poor and near-poor households with difficult lives, thanks to timely access to support programs and projects of the Party, the State, and social organizations along with suitable livelihood models, many families in highland communes have gradually stabilized their lives.
  • 'Accompanying taxpayers

    Accompanying taxpayers

    ECONOMY -
    ĐBP - The transition from flat tax to declaration-based tax starting in 2026 is assessed as a step suitable for modernization, transparency, and integration goals, but business households must adapt to a model completely different from long-standing habits.
  • 'Opening tourism opportunities for Điện Biên

    Opening tourism opportunities for Điện Biên

    TRAVEL -
    ĐBP - The completion of the Điện Biên Airport upgrade and its reopening in December 2023 has ushered in a new phase for transport infrastructure, laying a vital foundation for Điện Biên to gradually remove connectivity bottlenecks, expand its development space, and enhance its capacity to attract investment and tourism.
  • 'Proactive on-site fire prevention and fire fighting

    Proactive on-site fire prevention and fire fighting

    SOCIAL AFFAIRS -
    ĐBP - Whenever a fire or explosion occurs, no matter how professional the firefighting force is or how sensitive the response is, property damage is unavoidable. Therefore, for fire and explosion prevention and fighting, besides the responsibility of functional forces, the top important factor is strengthening proactiveness and timely rescue of on-site forces.
  • 'Solid foundation promotes sustainable tourism development in Điện Biên

    Solid foundation promotes sustainable tourism development in Điện Biên

    TRAVEL -
    ĐBP - After 5 years of implementing Resolution No.03-NQ/TU, dated May 7, 2021, of the Executive Board of the Điện Biên provincial Party Committee regarding Tourism Development until 2025, with orientation to 2030; based on available advantages, many potentials have been step-by-step awakened and effectively promoted.
  • 'Steel shield at Northwestern peak

    Steel shield at Northwestern peak

    SOCIAL AFFAIRS -
    ĐBP - 143 collectives and 775 individuals were honored with noble awards from the Party, the State, and the Ministry of Public Security. With sweat soaking the forest paths, with steel will amidst myriad dangers, the Điện Biên provincial Police force has built a fortress of peace at the peak of the Northwest sky, where every soldier is a fulcrum of trust for the people.