Điện Biên concentrates efforts to accelerate progress of major projects

ĐBP - Currently, some key projects in Điện Biên province are entering the final stage, making the deployment of construction and the disbursement of public investment capital increasingly urgent.

However, the reality shows that many construction works still face difficulties, especially site clearance issues affecting construction progress. Faced with this situation, departments, sectors, and localities are being required to focus highly, resolutely resolve remaining issues to ensure projects are completed on schedule.

The contractor unit concentrating human resources and machinery to accelerate the implementation progress of the Project for Preservation and Embellishment of the Him Lam Resistance Center Relic Area.

These days, on the construction site of the Project for Preservation and Embellishment of the Him Lam Resistance Center Relic Area (Phase II), the working atmosphere is urgent and rushed. From early morning until late at night, the construction units diligently stick to the site, working continuous shifts to ensure progress. Groups of workers are quickly deploying ground leveling, concrete revetment for the embankment slope, pouring concrete foundations for the relief, or constructing the wooden parts of the incense house with the determination to complete the work on schedule.

The project belongs to Group B, a Type III civil works project, with a total investment of VND 91 billion, including many important items such as a relief sculpture 45m long and 8.9m high; a hexagonal incense offering house; a square area system, parking lots... With the implementation period in 2023 - 2025, the project has achieved cumulative disbursement of over 60% of the allocated capital plan, with many items nearing completion.

The relief item being deployed and installed by the contractor unit at the site.

Đặng Văn Thiện from Phuc Linh Co., Ltd. said: “The large workload, spread over hilly terrain, makes construction difficult. To ensure progress, the company has mobilized workers to work overtime at night, but everyone is determined because this is a project of special historical significance.”

To date, items such as: the incense stele at strongpoint 1 - where Hero Phan Đình Giót sacrificed his life have been completed; the repair of the reception house, pouring concrete for the shaped embankment slope, deploying the drainage system... are being accelerated. Tô Văn Thuận, Management Board of Civil and Industrial Works Projects, said: Currently, the rough carving part of the relief item has been completed and is being installed at the site. Items like ground leveling, concrete revetment, the wooden part of the incense house, and paving stones on the roads leading up to the strongpoints are all being implemented simultaneously. In the coming time, the unit will continue to urge contractors to speed up progress, strengthen supervision, and perform disbursement and payment according to regulations.

The investor actively coordinating with Party committees and local governments for site clearance, creating conditions to accelerate project progress.

Previously, the Project Management Board and Land Fund Development of Area 1 highly focused on accelerating the progress of the project to build the resettlement area and sites for the provincial Administrative - Political Center Area, which is part of the plan to move the administrative-political center. With the goal of ensuring site clearance and completing technical infrastructure according to the roadmap, relevant units mobilized maximum human resources and equipment, especially for key bidding packages. Regarding site clearance, the investor has received handover from 44/46 households (corresponding to 12.15/12.58 hectares). From November 8 - 14, site clearance continued to be deployed, but problems persisted because residents did not agree to hand over the land.

Faced with that reality, the Project Management Board and Land Fund Development of Area 1 directed the contractors to set detailed schedules, concentrate human resources on bidding packages 2 and 3; and simultaneously coordinated with competent authorities to complete the dossiers for the Mường Thanh ward People’s Committee to issue a decision on mandatory land recovery for non-compliant households, ensuring the project is completed on schedule.

On the construction site of the transport project connecting key economic areas along National Highway 279 and National Highway 12 (the Dynamic Road project), the construction atmosphere in recent days has always been urgent, with contractors making maximum use of time in locations with clean sites. The entire route is over 35.3km long, with nearly 30km outside the urban area being focused on construction. However, the biggest difficulty currently lies in site clearance.

The construction unit accelerating the progress of the Dynamic Road project.

The project requires site clearance of over 83.28 hectares belonging to 1,751 households and 13 organizations. To date, localities have approved 99.73% of the area and actually handed over over 96.9% of the site, but problems still exist. In the 2022 - 2023 period, the site was handed over piecemeal, making it impossible to construct many road segments due to lack of access for equipment or lack of synchronous site clearance between the excavation and embankment parts. By 2024 - 2025, although the handover rate has reached over 97% in most localities, there are still cases of people who have not received money, have not dismantled assets, or deliberately obstruct construction.

To speed up the project implementation progress, the provincial Management Board of Transport Projects requested contractors to continue accelerating in locations that already have cleared sites; and simultaneously proposed that localities complete additional compensation procedures and resolutely handle cases of deliberate non-compliance. In parallel, working groups closely monitor the grassroots level, mobilize residents, ensuring a balance of legitimate interests to soon have enough synchronous sites for construction, striving to complete the project on schedule, creating a strategic traffic axis to promote the province’s economic development.

From now until the end of the year, time is short, and key projects in the province are entering the construction acceleration phase. Therefore, difficulties in compensation and site clearance must be resolved completely and resolutely. Especially for projects where the site handover is not synchronous, or where residents have not received compensation, have not handed over assets, or have arising complaints about compensation prices. This directly affects the construction progress and the disbursement of public investment capital.

Construction units implementing tasks belonging to the Nậm Rốm River Basin Multi-Hazard Management Project.

Faced with that situation, the Department of Finance requested investors to urgently focus resources and accelerate the implementation progress of projects scheduled for completion in 2025; resolutely and completely handle projects that have already had their implementation time extended. For key projects being deployed in Thanh Nưa, Thanh Yên communes and 2 wards: Mường Thanh, Điện Biên Phủ, site clearance must be prioritized immediately, ensuring the handover of a clean site according to the committed time milestones. The Department of Finance requested investors to focus on disbursement and payment of completed volumes, especially for projects that have been allocated sufficient capital needs according to the disbursement commitment.

Besides, the People’s Committees of communes, wards, and units assigned as investors need to closely follow the direction of the Standing Board of the provincial Party Committee and the provincial People’s Committee, focusing on construction, accelerating site clearance, and completing relevant dossiers and procedures. The units must seriously maintain a reporting regime, providing full information on the progress of key projects as required by the provincial People’s Committee, contributing to ensuring overall progress and promoting the effectiveness of public investment capital disbursement in 2025. From now until the end of the year, the requirement to complete key projects is increasingly urgent. Therefore, in addition to the decisive direction of the province and departments/sectors, investors and construction units need to continue maximizing resource mobilization, closely coordinating with localities to seriously fulfill their assigned responsibilities. When difficulties are resolved promptly, sites are handed over synchronously, and capital is disbursed on schedule, key infrastructure projects will soon be completed, creating an important driving force to promote the province’s socio-economic development in the coming period.

Phạm Quang
Comment

You have 500/500 characters left

Please enter 5 or more characters!!!

Recent news

  • 'Điện Biên makes efforts to find market for agricultural products

    Điện Biên makes efforts to find market for agricultural products

    ECONOMY -
    ĐBP - These days, some agricultural production areas in the province are entering the harvest season. Many types of agricultural products have been purchased right at the field by enterprises and traders as soon as they are ready for harvest. However, there are still some products with unstable outlets, and their consumption depends heavily on the market, causing inevitable anxiety among farmers.
  • 'Giving launchpad to young sports talents of Điện Biên

    Giving launchpad to young sports talents of Điện Biên

    CULTURE - SPORTS -
    ĐBP - The Education and Training sector’s first-place overall finish at the 12th Điện Biên provincial Sports Games in 2026 reflects the strong growth of school sports in the province. However, behind the medals still lies a gap in specialized training environments. The proposed establishment of a provincial Sports Talent High School is expected to create a breakthrough in discovering and nurturing high quality young athletes for the future.
  • 'For public health

    For public health

    SOCIAL AFFAIRS -
    ĐBP - Responding to the “Action Month for Food Safety” in 2026 with the theme “Ensuring food safety, preventing food poisoning in catering services and street food,” from April 15 to May 15, 2026, interdisciplinary inspection teams from the provincial to the commune and ward levels in Điện Biên simultaneously stepped up inspections and supervision at various establishments.
  • 'Điện Biên urgently prepares for high school graduation exam

    Điện Biên urgently prepares for high school graduation exam

    SOCIAL AFFAIRS -
    ĐBP - With only a few weeks left, the 2026 high school graduation exam will officially take place. This year, the exam features many new points; therefore, along with urgently completing the review program and consolidating knowledge for students, the Điện Biên provincial Education and Training sector is also actively preparing other conditions to ensure the exam takes place safely, strictly, and achieves high results.
  • 'Vietnam’s first border inter-level boarding school opens doors to future

    Vietnam’s first border inter-level boarding school opens doors to future

    SOCIAL AFFAIRS -
    ĐBP - After one semester studying under the roof of their new school, joy is clearly reflected in the eyes and smiles of students at Si Pa Phìn Inter-level Boarding School for Primary and Secondary Education in Si Pa Phìn commune, Điện Biên province - the first inter-level boarding school built in a border commune anywhere in the country.
  • 'Paving the way to the future

    Paving the way to the future

    ECONOMY -
    ĐBP - The Sơn La - Điện Biên - Tây Trang International Border Gate expressway project is identified by Điện Biên province as a key work, creating momentum to promote regional linkages, socio-economic development, and national defense and security in the Northwestern region. With high determination, site clearance work is being heavily promoted, along with the construction of resettlement areas and building consensus among the people to ensure the project is implemented on schedule.
  • 'Voices from years of wartime inspire new generation of Điện Biên

    Voices from years of wartime inspire new generation of Điện Biên

    NEWS - POLITICS -
    ĐBP - To help younger generations gain a deeper understanding of the value of peace, independence, and the nation’s glorious revolutionary traditions, the Điện Biên provincial Youth Union, in coordination with the provincial Veterans Association, organized a cultural exchange program titled “Stories from the years of wartime”. The event attracted a large number of youth union members and young people, creating a meaningful space for dialogue and firsthand historical storytelling from veterans.
  • 'Learning from Uncle Hồ in a border commune

    Learning from Uncle Hồ in a border commune

    NEWS - POLITICS -
    ĐBP - In the border commune of Mường Nhà, the movement of learning and following Hồ Chí Minh’s ideology, morality, and lifestyle is spreading increasingly widely. Every cadre, party member, and citizen in the commune has been actively learning and following Uncle Hồ through specific and practical actions.
  • 'Spreading “Digital Party cell” and “Digital family” models

    Spreading “Digital Party cell” and “Digital family” models

    NEWS - POLITICS -
    ĐBP - Digital transformation is becoming an inevitable trend, profoundly impacting all areas of social life. In this context, bringing technology closer to the people, especially women in rural and ethnic minority areas, is identified as an important task, contributing to bridging the digital divide and creating a foundation for building a digital society.
  • 'Điện Biên works with French Development Agency

    Điện Biên works with French Development Agency

    ECONOMY -
    ĐBP - On May 19, Permanent Vice Chairman of the Điện Biên provincial People’s Committee Lò Văn Cương had a working session with the delegation of the French Development Agency (AFD), led by Olivier Gilard, Project Manager at the Water and Sanitation Division at AFD Headquarters.
  • 'Transportation equation in tourism development

    Transportation equation in tourism development

    TRAVEL -
    ĐBP - Besides its historical advantages, Điện Biên also possesses villages rich in cultural identity and pristine, attractive natural landscapes. This is considered the province’s potential for developing community tourism.
  • 'Building strong “roots” for the Party

    Building strong “roots” for the Party

    NEWS - POLITICS -
    ĐBP - Party member development is one of the key tasks in Party building at the grassroots level. The sourcing and fostering of the elite masses have been implemented synchronously, contributing to enhancing the leadership capacity and combat strength of Party organizations.