Điện Biên concentrates efforts to accelerate progress of major projects

ĐBP - Currently, some key projects in Điện Biên province are entering the final stage, making the deployment of construction and the disbursement of public investment capital increasingly urgent.

However, the reality shows that many construction works still face difficulties, especially site clearance issues affecting construction progress. Faced with this situation, departments, sectors, and localities are being required to focus highly, resolutely resolve remaining issues to ensure projects are completed on schedule.

The contractor unit concentrating human resources and machinery to accelerate the implementation progress of the Project for Preservation and Embellishment of the Him Lam Resistance Center Relic Area.

These days, on the construction site of the Project for Preservation and Embellishment of the Him Lam Resistance Center Relic Area (Phase II), the working atmosphere is urgent and rushed. From early morning until late at night, the construction units diligently stick to the site, working continuous shifts to ensure progress. Groups of workers are quickly deploying ground leveling, concrete revetment for the embankment slope, pouring concrete foundations for the relief, or constructing the wooden parts of the incense house with the determination to complete the work on schedule.

The project belongs to Group B, a Type III civil works project, with a total investment of VND 91 billion, including many important items such as a relief sculpture 45m long and 8.9m high; a hexagonal incense offering house; a square area system, parking lots... With the implementation period in 2023 - 2025, the project has achieved cumulative disbursement of over 60% of the allocated capital plan, with many items nearing completion.

The relief item being deployed and installed by the contractor unit at the site.

Đặng Văn Thiện from Phuc Linh Co., Ltd. said: “The large workload, spread over hilly terrain, makes construction difficult. To ensure progress, the company has mobilized workers to work overtime at night, but everyone is determined because this is a project of special historical significance.”

To date, items such as: the incense stele at strongpoint 1 - where Hero Phan Đình Giót sacrificed his life have been completed; the repair of the reception house, pouring concrete for the shaped embankment slope, deploying the drainage system... are being accelerated. Tô Văn Thuận, Management Board of Civil and Industrial Works Projects, said: Currently, the rough carving part of the relief item has been completed and is being installed at the site. Items like ground leveling, concrete revetment, the wooden part of the incense house, and paving stones on the roads leading up to the strongpoints are all being implemented simultaneously. In the coming time, the unit will continue to urge contractors to speed up progress, strengthen supervision, and perform disbursement and payment according to regulations.

The investor actively coordinating with Party committees and local governments for site clearance, creating conditions to accelerate project progress.

Previously, the Project Management Board and Land Fund Development of Area 1 highly focused on accelerating the progress of the project to build the resettlement area and sites for the provincial Administrative - Political Center Area, which is part of the plan to move the administrative-political center. With the goal of ensuring site clearance and completing technical infrastructure according to the roadmap, relevant units mobilized maximum human resources and equipment, especially for key bidding packages. Regarding site clearance, the investor has received handover from 44/46 households (corresponding to 12.15/12.58 hectares). From November 8 - 14, site clearance continued to be deployed, but problems persisted because residents did not agree to hand over the land.

Faced with that reality, the Project Management Board and Land Fund Development of Area 1 directed the contractors to set detailed schedules, concentrate human resources on bidding packages 2 and 3; and simultaneously coordinated with competent authorities to complete the dossiers for the Mường Thanh ward People’s Committee to issue a decision on mandatory land recovery for non-compliant households, ensuring the project is completed on schedule.

On the construction site of the transport project connecting key economic areas along National Highway 279 and National Highway 12 (the Dynamic Road project), the construction atmosphere in recent days has always been urgent, with contractors making maximum use of time in locations with clean sites. The entire route is over 35.3km long, with nearly 30km outside the urban area being focused on construction. However, the biggest difficulty currently lies in site clearance.

The construction unit accelerating the progress of the Dynamic Road project.

The project requires site clearance of over 83.28 hectares belonging to 1,751 households and 13 organizations. To date, localities have approved 99.73% of the area and actually handed over over 96.9% of the site, but problems still exist. In the 2022 - 2023 period, the site was handed over piecemeal, making it impossible to construct many road segments due to lack of access for equipment or lack of synchronous site clearance between the excavation and embankment parts. By 2024 - 2025, although the handover rate has reached over 97% in most localities, there are still cases of people who have not received money, have not dismantled assets, or deliberately obstruct construction.

To speed up the project implementation progress, the provincial Management Board of Transport Projects requested contractors to continue accelerating in locations that already have cleared sites; and simultaneously proposed that localities complete additional compensation procedures and resolutely handle cases of deliberate non-compliance. In parallel, working groups closely monitor the grassroots level, mobilize residents, ensuring a balance of legitimate interests to soon have enough synchronous sites for construction, striving to complete the project on schedule, creating a strategic traffic axis to promote the province’s economic development.

From now until the end of the year, time is short, and key projects in the province are entering the construction acceleration phase. Therefore, difficulties in compensation and site clearance must be resolved completely and resolutely. Especially for projects where the site handover is not synchronous, or where residents have not received compensation, have not handed over assets, or have arising complaints about compensation prices. This directly affects the construction progress and the disbursement of public investment capital.

Construction units implementing tasks belonging to the Nậm Rốm River Basin Multi-Hazard Management Project.

Faced with that situation, the Department of Finance requested investors to urgently focus resources and accelerate the implementation progress of projects scheduled for completion in 2025; resolutely and completely handle projects that have already had their implementation time extended. For key projects being deployed in Thanh Nưa, Thanh Yên communes and 2 wards: Mường Thanh, Điện Biên Phủ, site clearance must be prioritized immediately, ensuring the handover of a clean site according to the committed time milestones. The Department of Finance requested investors to focus on disbursement and payment of completed volumes, especially for projects that have been allocated sufficient capital needs according to the disbursement commitment.

Besides, the People’s Committees of communes, wards, and units assigned as investors need to closely follow the direction of the Standing Board of the provincial Party Committee and the provincial People’s Committee, focusing on construction, accelerating site clearance, and completing relevant dossiers and procedures. The units must seriously maintain a reporting regime, providing full information on the progress of key projects as required by the provincial People’s Committee, contributing to ensuring overall progress and promoting the effectiveness of public investment capital disbursement in 2025. From now until the end of the year, the requirement to complete key projects is increasingly urgent. Therefore, in addition to the decisive direction of the province and departments/sectors, investors and construction units need to continue maximizing resource mobilization, closely coordinating with localities to seriously fulfill their assigned responsibilities. When difficulties are resolved promptly, sites are handed over synchronously, and capital is disbursed on schedule, key infrastructure projects will soon be completed, creating an important driving force to promote the province’s socio-economic development in the coming period.

Phạm Quang
Comment

You have 500/500 characters left

Please enter 5 or more characters!!!

Recent news

  • 'Bringing preferential loans to locals

    Bringing preferential loans to locals

    BUSINESS -
    ĐBP - In recent times, the Vietnam Bank for Social Policies (VBSP), along with Party committees and local governments, has made efforts to bring preferential loan capital to the people, especially poor households and vulnerable groups.
  • 'Điện Biên works with KOICA Office in Vietnam

    Điện Biên works with KOICA Office in Vietnam

    NEWS - POLITICS -
    ĐBP - On November 24, Vice Chairman of the provincial People’s Committee Lò Văn Cương worked with the KOICA Office in Vietnam regarding the survey and preparation for the implementation of the project “Enhancing self-reliance capacity for rural areas through building electricity infrastructure for disadvantaged regions of Điện Biên province.”
  • 'Early stabilization of life for Huổi Có residents

    Early stabilization of life for Huổi Có residents

    SOCIAL AFFAIRS -
    ĐBP - The recent heavy rains in early August significantly disrupted the lives of the residents of Huổi Có village, Phình Giàng commune, Điện Biên province. Many households had to leave their old homes, the road to the village was cut off, and daily life was difficult. There is an urgent need to quickly stabilize their lives, ensuring safe accommodation so that people can feel secure in their daily activities, studies, and production.
  • 'For the cause of “cultivating people”

    For the cause of “cultivating people”

    SOCIAL AFFAIRS -
    ĐBP - In the 2020 - 2025 period, despite facing many difficulties regarding human resources and financial resources, the education and training sector of Điện Biên province has consistently maintained a spirit of innovation, creativity, and persistent effort to overcome challenges and complete key objectives.
  • 'Provincial People’s Committee holds November session

    Provincial People’s Committee holds November session

    NEWS - POLITICS -
    ĐBP - On the evening of November 23, the Điện Biên provincial People’s Committee held its November session, co-chaired by comrades: Lê Văn Lương, Deputy Secretary of the provincial Party Committee, Chairman of the provincial People’s Committee; Lò Văn Cương, Member of the provincial Party Committee Standing Committee, Vice Chairman of the provincial People’s Committee.
  • 'Điện Biên records breakthrough in digital transformation

    Điện Biên records breakthrough in digital transformation

    SOCIAL AFFAIRS -
    ĐBP - In the process of building an e-government and promoting digital transformation, Điện Biên province identifies the reception, resolution, and return of results for administrative procedures (APs) via the Online Public Service Portal as one of the key tasks. This is not only an inevitable trend but has also become an important driving force creating strong changes in administrative reform, improving service quality, and enhancing the transparency and efficiency of the two-tier local government apparatus.
  • 'Mường Luân ancient tower by Mã River

    Mường Luân ancient tower by Mã River

    CULTURE - TOURISM -
    ĐBP - After being restored and renovated with a spacious and refined appearance, the Mường Luân ancient tower by the Mã River is gradually becoming a new, attractive destination on the tourism map of Mường Luân commune.
  • 'Solidifying people’s defense posture

    Solidifying people’s defense posture

    NEWS - POLITICS -
    ĐBP - In recent years, along with the mission of training and combat readiness, the Điện Biên provincial Border Guard forces have consistently maintained field expeditions associated with mass mobilization efforts, supporting economic development, and participating in consolidating the grassroots political system, focusing on the border area. These practical actions have built the people’s trust and have been recognized by local Party committees and governments.
  • 'Creating seed sources on Mường Thanh rice field

    Creating seed sources on Mường Thanh rice field

    BUSINESS -
    ĐBP - Currently, residents in the province are using rice seeds imported from other units and localities, as no enterprise or cooperative yet self-produces rice seeds characteristic of the Mường Thanh rice field. The lack of a stable indigenous seed source not only makes production dependent on external supply but also becomes a concern for the entire agricultural sector.
  • 'Culture takes root in community life

    Culture takes root in community life

    CULTURE - TOURISM -
    ĐBP - Enhancing the cultural and spiritual life of residents is a key task in building cohesive, culturally rich communities. With that goal, the Department of Culture, Sports and Tourism of Điện Biên province has implemented a wide range of grassroots - focused activities, contributing to the preservation and promotion of traditional cultural values and fostering a healthy, sustainable cultural environment in every village and neighborhood.
  • 'Na Son arouses spirit of self-reliance and self-improvement

    Na Son arouses spirit of self-reliance and self-improvement

    NEWS - POLITICS -
    ĐBP - Na Son commune was established based on the merger of Na Son commune, Keo Lôm commune, and Điện Biên Đông town. After the merger, Na Son commune still faces many difficulties: An asynchronous infrastructure, a high poverty rate, and continuous natural disasters... But it is precisely in these hardships that the spirit of studying and following President Hồ Chí Minh’s ideology, ethics, and style has become a spiritual anchor, creating the strength of solidarity and the aspiration for change.
  • 'Điện Biên’s cultural heritage considered tourism potential

    Điện Biên’s cultural heritage considered tourism potential

    CULTURE - TOURISM -
    ĐBP - Exploiting the value of cultural heritage to achieve the goal of developing tourism into a key economic sector of the province. This is a goal that Điện Biên can fully achieve because the province possesses a rich and diverse system of tangible and intangible cultural heritage, along with the national historical relic complex of the Điện Biên Phủ battlefield.