Điện Biên concentrates efforts to accelerate progress of major projects

ĐBP - Currently, some key projects in Điện Biên province are entering the final stage, making the deployment of construction and the disbursement of public investment capital increasingly urgent.

However, the reality shows that many construction works still face difficulties, especially site clearance issues affecting construction progress. Faced with this situation, departments, sectors, and localities are being required to focus highly, resolutely resolve remaining issues to ensure projects are completed on schedule.

The contractor unit concentrating human resources and machinery to accelerate the implementation progress of the Project for Preservation and Embellishment of the Him Lam Resistance Center Relic Area.

These days, on the construction site of the Project for Preservation and Embellishment of the Him Lam Resistance Center Relic Area (Phase II), the working atmosphere is urgent and rushed. From early morning until late at night, the construction units diligently stick to the site, working continuous shifts to ensure progress. Groups of workers are quickly deploying ground leveling, concrete revetment for the embankment slope, pouring concrete foundations for the relief, or constructing the wooden parts of the incense house with the determination to complete the work on schedule.

The project belongs to Group B, a Type III civil works project, with a total investment of VND 91 billion, including many important items such as a relief sculpture 45m long and 8.9m high; a hexagonal incense offering house; a square area system, parking lots... With the implementation period in 2023 - 2025, the project has achieved cumulative disbursement of over 60% of the allocated capital plan, with many items nearing completion.

The relief item being deployed and installed by the contractor unit at the site.

Đặng Văn Thiện from Phuc Linh Co., Ltd. said: “The large workload, spread over hilly terrain, makes construction difficult. To ensure progress, the company has mobilized workers to work overtime at night, but everyone is determined because this is a project of special historical significance.”

To date, items such as: the incense stele at strongpoint 1 - where Hero Phan Đình Giót sacrificed his life have been completed; the repair of the reception house, pouring concrete for the shaped embankment slope, deploying the drainage system... are being accelerated. Tô Văn Thuận, Management Board of Civil and Industrial Works Projects, said: Currently, the rough carving part of the relief item has been completed and is being installed at the site. Items like ground leveling, concrete revetment, the wooden part of the incense house, and paving stones on the roads leading up to the strongpoints are all being implemented simultaneously. In the coming time, the unit will continue to urge contractors to speed up progress, strengthen supervision, and perform disbursement and payment according to regulations.

The investor actively coordinating with Party committees and local governments for site clearance, creating conditions to accelerate project progress.

Previously, the Project Management Board and Land Fund Development of Area 1 highly focused on accelerating the progress of the project to build the resettlement area and sites for the provincial Administrative - Political Center Area, which is part of the plan to move the administrative-political center. With the goal of ensuring site clearance and completing technical infrastructure according to the roadmap, relevant units mobilized maximum human resources and equipment, especially for key bidding packages. Regarding site clearance, the investor has received handover from 44/46 households (corresponding to 12.15/12.58 hectares). From November 8 - 14, site clearance continued to be deployed, but problems persisted because residents did not agree to hand over the land.

Faced with that reality, the Project Management Board and Land Fund Development of Area 1 directed the contractors to set detailed schedules, concentrate human resources on bidding packages 2 and 3; and simultaneously coordinated with competent authorities to complete the dossiers for the Mường Thanh ward People’s Committee to issue a decision on mandatory land recovery for non-compliant households, ensuring the project is completed on schedule.

On the construction site of the transport project connecting key economic areas along National Highway 279 and National Highway 12 (the Dynamic Road project), the construction atmosphere in recent days has always been urgent, with contractors making maximum use of time in locations with clean sites. The entire route is over 35.3km long, with nearly 30km outside the urban area being focused on construction. However, the biggest difficulty currently lies in site clearance.

The construction unit accelerating the progress of the Dynamic Road project.

The project requires site clearance of over 83.28 hectares belonging to 1,751 households and 13 organizations. To date, localities have approved 99.73% of the area and actually handed over over 96.9% of the site, but problems still exist. In the 2022 - 2023 period, the site was handed over piecemeal, making it impossible to construct many road segments due to lack of access for equipment or lack of synchronous site clearance between the excavation and embankment parts. By 2024 - 2025, although the handover rate has reached over 97% in most localities, there are still cases of people who have not received money, have not dismantled assets, or deliberately obstruct construction.

To speed up the project implementation progress, the provincial Management Board of Transport Projects requested contractors to continue accelerating in locations that already have cleared sites; and simultaneously proposed that localities complete additional compensation procedures and resolutely handle cases of deliberate non-compliance. In parallel, working groups closely monitor the grassroots level, mobilize residents, ensuring a balance of legitimate interests to soon have enough synchronous sites for construction, striving to complete the project on schedule, creating a strategic traffic axis to promote the province’s economic development.

From now until the end of the year, time is short, and key projects in the province are entering the construction acceleration phase. Therefore, difficulties in compensation and site clearance must be resolved completely and resolutely. Especially for projects where the site handover is not synchronous, or where residents have not received compensation, have not handed over assets, or have arising complaints about compensation prices. This directly affects the construction progress and the disbursement of public investment capital.

Construction units implementing tasks belonging to the Nậm Rốm River Basin Multi-Hazard Management Project.

Faced with that situation, the Department of Finance requested investors to urgently focus resources and accelerate the implementation progress of projects scheduled for completion in 2025; resolutely and completely handle projects that have already had their implementation time extended. For key projects being deployed in Thanh Nưa, Thanh Yên communes and 2 wards: Mường Thanh, Điện Biên Phủ, site clearance must be prioritized immediately, ensuring the handover of a clean site according to the committed time milestones. The Department of Finance requested investors to focus on disbursement and payment of completed volumes, especially for projects that have been allocated sufficient capital needs according to the disbursement commitment.

Besides, the People’s Committees of communes, wards, and units assigned as investors need to closely follow the direction of the Standing Board of the provincial Party Committee and the provincial People’s Committee, focusing on construction, accelerating site clearance, and completing relevant dossiers and procedures. The units must seriously maintain a reporting regime, providing full information on the progress of key projects as required by the provincial People’s Committee, contributing to ensuring overall progress and promoting the effectiveness of public investment capital disbursement in 2025. From now until the end of the year, the requirement to complete key projects is increasingly urgent. Therefore, in addition to the decisive direction of the province and departments/sectors, investors and construction units need to continue maximizing resource mobilization, closely coordinating with localities to seriously fulfill their assigned responsibilities. When difficulties are resolved promptly, sites are handed over synchronously, and capital is disbursed on schedule, key infrastructure projects will soon be completed, creating an important driving force to promote the province’s socio-economic development in the coming period.

Phạm Quang
Comment

You have 500/500 characters left

Please enter 5 or more characters!!!

Recent news

  • 'Bringing women together through clubs and community initiatives

    Bringing women together through clubs and community initiatives

    SOCIAL AFFAIRS -
    ĐBP - With more than 103,000 members across 888 local branches, the Điện Biên provincial Women’s Union is renewing its approach to engaging and mobilizing women through community-based initiatives, clubs and grassroots emulation campaigns. Each activity creates opportunities for women to meet, build bonds and work together on practical initiatives that benefit their families and communities.
  • 'Proud of tradition - steadfastly advancing toward the future

    Proud of tradition - steadfastly advancing toward the future

    SOCIAL AFFAIRS -
    ĐBP - Through 70 years of establishment and development (October 15, 1956 - 2026), Điện Biên provincial Ethnic Boarding High School has persistently overcome hardships, progressively asserting its standing in education and human resource training for the locality. Promoting the proud heritage of preceding generations, the school continues to innovate, elevate educational quality, and nurture knowledge and aspirations to excel among ethnic minority students across the province.
  • 'Young volunteers bring digital skills to the community

    Young volunteers bring digital skills to the community

    SOCIAL AFFAIRS -
    ĐBP – As part of the “Digital literacy for all” campaign, the Youth Union of Mường Tùng commune is taking a hands-on approach to digital inclusion, visiting villages and households to help residents use smartphones and access services that make everyday life easier. Starting with basic operations, young volunteers are helping local people, especially older residents, gradually develop digital skills and gain confidence in using technology.
  • 'Serving the people

    Serving the people

    NEWS - POLITICS -
    ĐBP - During his lifetime, President Hồ Chí Minh affirmed: “Cadres are the root of all work.” Therefore, building a contingent of cadres truly close to the people, attuned to the grassroots, understanding of the citizenry, and accountable to the public is the decisive factor in translating guidelines and policies into practical reality.
  • 'Turning national programs into tangible gains for farmers

    Turning national programs into tangible gains for farmers

    ECONOMY -
    ĐBP - Under the national target programs, Điện Biên province is focusing resources on helping local residents expand production, restructure crops and gradually establish raw-material zones linked to market outlets. By tailoring support to local needs, supplying seedlings, providing technical guidance and connecting farmers with businesses committed to purchasing their produce, the programs are helping increase the value of agricultural products, create sustainable livelihoods, reduce poverty and promote local economic development.
  • 'Languages and the ballot (Part 1)

    Languages and the ballot (Part 1)

    NEWS - POLITICS -
    ĐBP - A total of 99.96% of voters participated in the election of deputies to the 16th National Assembly and deputies to People’s Councils at all levels for the 2026-2031 tenure, placing Điện Biên among the top five provinces and centrally administered cities with the highest voter turnout nationwide. This also stands as the highest turnout rate the province has recorded across election cycles.
  • 'Traditional sports spread cultural colors of Hmông ethnic group

    Traditional sports spread cultural colors of Hmông ethnic group

    CULTURE - SPORTS -
    ĐBP - Thrilling tug-of-war and stick-pushing matches, deft pa pao throws, the resonant buzz of tù lu spinning tops, and intense concentration in every crossbow shooting round... All came together to forge a distinct appeal for the sporting competitions at the 4th Hmông Ethnic Cultural Festival. Through each contest, traditional sports delivered exciting moments, captivating residents and visitors while helping spread the cultural beauty of the Hmông people.
  • 'Closing ceremony of 4th Hmông Ethnic Cultural Festival

    Closing ceremony of 4th Hmông Ethnic Cultural Festival

    CULTURE - SPORTS -
    ĐBP - On the evening of October 11, at Mường Thanh Walking Street in Điện Biên Phủ ward, the Ministry of Culture, Sports and Tourism coordinated with the Điện Biên provincial People’s Committee to organize the Closing Ceremony of the 4th Hmông Ethnic Cultural Festival, 2026. Following three vibrant days featuring distinctive activities, the festival concluded with great success, leaving profound impressions on local residents and tourists.
  • 'Điện Biên improves domestic water quality

    Điện Biên improves domestic water quality

    SOCIAL AFFAIRS -
    ĐBP - From invested and upgraded water supply facilities to pipeline systems extending into residential areas, Điện Biên is progressively bringing clean water closer to the people. Alongside expanding supply networks, the province prioritizes water resource protection, elevating treatment quality, and strengthening surveillance, aiming to ensure safe, stable domestic water sources and contributing to improved public health and quality of life.
  • 'Adding diverse experiences for visitors

    Adding diverse experiences for visitors

    TRAVEL -
    ĐBP - Điện Biên is refreshing its tourism offerings with experiences linked to indigenous culture, community life, border regions, and urban nightlife spaces. These new products not only provide visitors with more choices, but also offer more intimate perspectives on the land and people of Điện Biên, helping lengthen stays and heighten destination appeal.