As of November 15, the province is expected to have disbursed VND 4,295 billion in public investment capital, equivalent to 88% of the plan, including funds carried over from previous years. Of this, approximately VND 4,154 billion comes from the 2026 capital plan, representing 84.12% of the allocation assigned by the Prime Minister.
Among the 14 inter-level schools being built across the province, nine had been completed and put into operation before the start of the new school year, with VND 1,542 billion disbursed, equivalent to 87.36% of the allocated capital. For the five schools whose construction began in 2026, project owners are stepping up construction, with disbursement reaching VND 754.8 billion, or 86.76% of the plan.
Vũ Văn Ngọc, Director of the Civil and Industrial Construction Project Management Board, said: “We have identified the inter-level school projects as a key priority, requiring preferential resource allocation and close oversight. The project management board regularly coordinates with contractors to inspect progress at construction sites, promptly address emerging difficulties, and urge the completion of acceptance and payment documentation for work already carried out. Our aim is to ensure that disbursement keeps pace with construction while maintaining quality, so that the projects can be put into operation soon and used effectively.”
For the Disaster-Resilient Rural Development Project, Điện Biên has allocated VND 216.603 billion in capital for 2026. By November 15, disbursement is expected to exceed VND 214 billion, or 98.94% of the allocation, broadly meeting the required schedule. Meanwhile, the Nậm Rốm River Basin Multi-Disaster Management Project, which aims to protect local communities, adapt to climate change and support socio-economic development, has been allocated VND 266.388 billion. More than VND 229.660 billion has been disbursed, equivalent to 86.21%.
As a project of strategic importance for regional connectivity, expanding development opportunities and driving the province’s socio-economic growth, the Sơn La-Điện Biên Expressway project has seen construction begin at several resettlement sites. Relevant agencies are also preparing and appraising feasibility study reports. With a substantial volume of work still to be completed and the end of the budget year approaching, accelerating investment procedures, land clearance and the implementation of project components will be crucial to achieving the project's targets.
Trần Thanh Kiên, Director of the provincial Transport Construction Project Management Board, said: “We are working with departments, agencies and local authorities to address each issue, particularly those involving compensation, support and resettlement. At the same time, we are accelerating investment preparation procedures to ensure the project is ready for implementation according to schedule.”
In practice, the implementation of key projects is affected by a range of factors. According to the Department of Finance, major obstacles include difficulties in land clearance and capital allocation. Some projects have yet to receive full site handovers, preventing construction from proceeding simultaneously across all sections. In addition, investment procedures and the disbursement of ODA funds can be time-consuming, as some projects must complete revised documentation, withdrawal procedures and payment requirements set by donors. At certain construction sites, although work has already been carried out, acceptance procedures and payment documentation have not been completed in a timely manner. The construction capacity of some contractors also needs to improve, particularly in mobilizing sufficient workers, machinery and equipment to meet schedule requirements.
To ensure the 2026 capital plan is fulfilled, the Department of Finance will continue advising the provincial People’s Committee on coordinated measures, prioritizing projects with strong disbursement potential and key infrastructure works. Project owners are required to prepare detailed construction and disbursement schedules for each week through December 31, 2026, and directly supervise and urge contractors to mobilize additional workers, machinery and equipment. Where conditions permit, construction should be organized around the clock, with three shifts and four work teams. Acceptance and payment procedures must be completed as soon as work volumes are finished, rather than being left until the end of the year.
Regarding land clearance, departments, agencies and local authorities must focus on resolving outstanding issues involving compensation, support and resettlement, and promptly hand over sites to project owners and contractors. They must also accelerate land auctions, bidding procedures and land price determination to secure revenue and funding for projects as planned.
The Department of Finance will continue monitoring disbursement results on a weekly basis and coordinating with State Treasury Region X to resolve issues related to fund control and payment. It will also review and advise on reallocating capital from completed projects, projects with no further funding needs, or those unlikely to disburse their allocations to projects with completed work, outstanding payment needs and stronger disbursement capacity.
The province aims to disburse 100% of its allocated capital by the end of the year while ensuring that each project meets construction schedules, quality standards and investment efficiency requirements. Achieving this goal requires coordinated and decisive action from all levels of government, sectors and localities, with particular accountability resting on the heads of project-owning agencies. Accelerating construction and disbursement for key projects will help ensure their timely completion and effective operation, improve the use of public investment resources, and prevent situations in which funds remain idle while projects fall behind schedule. This will enable major projects to deliver tangible benefits to the province sooner.